Britain paid wind farms £52.7m to turn down 1,950 GWh in October, its biggest month of curtailment this year

source: reddit (reddit:energy)published 2026-11-01 10:36ingested 2026-11-02 02:41

retained text

October has just ended up as Britain's biggest month this year for wind being turned down by the grid operator (NESO).

The final figure is 1,950 GWh turned down in October at a net cost of £52.7m. That's about 21% of what Britain's grid-scale wind farms could have made. For comparison, September was 1,813 GWh and January was 1,231 GWh.

The three biggest single days of the entire year are also all in October. Tuesday 27 October was the top one at 169 GWh and £6.67m net. On Sunday 4 October about 41% of possible grid-scale wind output was turned down.

The reason is almost entirely about transmission, not too much wind overall. Most of the big wind is in the north, most of the demand is in the south, and the lines between them fill up on windy days. So NESO pays wind in the north to turn down and usually pays gas plants further south to turn up.

One odd quirk is that September cost more (£54.7m net) for less wind. Some farms on Contracts for Difference pay to turn down instead of being paid, which pulls the net cost down. One big offshore farm came out at minus £7.19m net in October.

This is a perfect example of why grid build-out is so critical for the UK's energy infrastructure. 

A few caveats... the cost is a net figure, the numbers are indicative from Elexon's settlement data and can be revised, and the percentages only count the big transmission connected farms.

Source: [https://electricitylive.com/curtailment](https://electricitylive.com/curtailment)