Softbank logs $3.7 billion loss on canceled 13GW of power generation equipment for AIDCs, days after denying Musk’s default claim

source: reddit (reddit:stocks)published 2026-11-11 18:39ingested 2026-11-12 02:40

retained text

SoftBank is taking a **$3.7 billion hit to earnings** after canceling reservations for **13 GW of natural gas turbines** originally ordered to power future AI data centers. While CFO Yoshimitsu Goto strongly denied Elon Musk’s claims that SoftBank defaulted, the write-down highlights the risks of speculative over-ordering in AI power infrastructure.

\---

# Key Takeaways

\* **Financial Hit:** SoftBank absorbs a **$3.7B earnings drag** to unwind turbine supply contracts with **GE Vernova** and other suppliers after overestimating near-term power demand.

\* **Massive Scale:** Canceled reservations totaled **13 gigawatts:** more than six Hoover Dams' worth of capacity and equivalent to the total power consumption of Connecticut.

\* **The Speculative Bet:** SoftBank attempted to corner the gas turbine market years in advance, expecting AI-driven supply shortages would make the hardware indispensable.

\* **Current Projects:** SoftBank is still planning a **$33 billion, 9.2 GW gas power plant in Ohio** (slated for 2027) to feed an 8 GW data center leased to **OpenAI**, with **Nvidia** in discussions to guarantee \~$250B in financing.

\* **The PR Feud:** Follows claims by xAI CEO Elon Musk that SoftBank defaulted on turbine blade contracts. SoftBank’s CFO countered that the cancellation was a **voluntary strategic shift**, not a financial default.

https://www.tomshardware.com/tech-industry/data-centers/softbank-loses-usd3-7-billion-on-canceled-ai-data-center-gas-turbine-orders-days-after-denying-elon-musks-claim-it-was-defaulting-company-kills-reserved-13-gigawatts-of-power-more-than-six-hoover-dams-worth-of-capacity